A Time to Build

(click image to enlarge)
 
Compacting Ground for Forms - 8-13-08
Rebar and Forms Ready for First Concrete Pour - 8-13-08
Concrete Forms and Re-bar Arrive - 8-12-08
Concrete Forms for North Wall - 8-12-08
  • The church office building was demolished Thursday, July 10th.
  • The in-ground oil tank was removed Friday, July 11th with a little extra needed hydraulic power. Seems somebody had an idea to bolt it down to a cement pad so it wouldn’t pop out of the ground. The Lord preserved the tank from leaking fuel into the soil, like He knew that He was going to have FBC construct a new life center in the year 2008, what perfect timing!!!!
  • Pastor Sheranko drove to South Hadley to get all the paperwork so we didn’t lose a day waiting for the mail to come to FBC. Thanks Pastor Tim.
  • We close with the Bank on Monday!!!!
  • Western Builders plans on bringing some equipment in on the 15th, but not much they can do until we are issued the building permit.
  • Ground Breaking took place Sunday, May 4th.
Digging for the North wall - 8-11-08
Digging for the South wall - 8-11-08
Front Foundation Wall - 8-8-08
Rain Delay, 8-6-08